The loft conversion process

Stage 1

Scaffold erected on the front, rear and in some instances side of the property. We then create an opening to the front of the roof to gain access to the loft. The steels (RSJ’s) are then installed.

Stage 2

The floor joists are then fitted, Velux windows installed and dormer construction if required.

Stage 3

Roof tiled, dormer construction completed if required.

Stage 4

Electrical wiring and plumbing installed, a new opening is created to make room for a new staircase.

Stage 5

Insulation, plaster boards fitted, internal walls built, plastering finished.

Stage 6

2nd fixing including skirting, door frames etc also light switches and power plugs, en-suite installed if required, all finishes completed leaving your property clean and tidy.

The loft conversion is now ready for you to decorate, however this is something we can carry out if you wish.